The turbine resumed its operation to the successful conclusion of the first large wind corrective managed entirely by Argentine technicians

_____

Genneia After spending 139 days out of service, the wind turbine # 3 of our Trelew Wind Farm produce energy again thanks to the work of a team of technicians Genneia own. The work consisted of replacing the generator, a challenge that required high-level maneuver loads of 13 tonnes by a crane large size. cleaning is also made of the blades to optimize their performance and service life.

The commissioning of the aero # 3 represents the first major milestone in the maintenance activity in house of wind farms, initiated by Genneia in 2020. Until then, maintaining all of our wind centers was provided by staff technologist (firm responsible for the manufacture, installation and testing of wind turbines), under maintenance contracts full service .

Throughout 2019, the group Genneia technicians were trained to take on this task, and before the challenge of the aero # 3, counted to his credit and several repairs up tower . Genneia is a leader in wind power in Argentina: its 236 wind turbines installed nationwide supply of clean energy for 700,000 homes, and way of generating efficient and friendly to the environment brings savings of 1,520,000 tons of CO2 emissions. With the landing of maintenance in house , the company writes a new page in this story.


SHARE