Roads ready. the first concreting was performed and the transfer of components is planned. Strong>
a>
Within the time provided, works for the installation of 38 wind turbines that will integrate stages II, III and IV of the North Wind Farm Chubut moving at a fast pace. On July 3 it began with the first concrete foundation where the turbines will be installed and is expected to continue with intense activities despite the climate that has been with minimum temperatures below zero and maximum not exceeding 4 ° C in Puerto Madryn .
During the month of August, transport equipment special dimensions of the company ROMAN will proceed to the transfer of the circulating components from the port Provincial Route 1, then the national to the northern route A010 to the RN 3 and from there to access Chubut to North Wind Park. All public security operations will be coordinated between the company and entities responsible for municipal, provincial and national roads.
Chubut Norte consists of four construction phases. The first, Chubut Norte I already in operation and was inaugurated by the President in January, it has an installed capacity of 28.8 MW.
Stages II, III and IV, currently under development, will have an installed capacity of 167 MW and will generate 779,900 MWh annually that will turn to the SADI. This is equivalent to the consumption of 233,000 households in Argentina and reduced emission into the atmosphere of 268,000 tons of CO2