The farm comes out from two constructive projects. Arising from RenovAr 1.5, Pomona I (101.4MW) entered into operation in July 2019. For its construction, Genneia obtained a financing of US$ 142 million, under Project Finance modality, granted by German development banks KFW and DEG and guarantee Euler Hermes.

Moreover, Pomona II (11.7MW) was originated within a Sale to Private or Great Users agreement framework signed between Genneia and AMCOR, ARLEI and MERANOL companies.

With a certified saving of 200,000 t of C02 emissions per year, as from 2020 our Pomona Wind Farm is authorized by the organization Verified Carbon Standard to issue Reduction Emissions Certificates.

EXCELLENCE INDICATOR

The load factor of Pomona Wind Farm is among the highest in the world, in both stages of the centre:

  • Pomona I: 45.1%
  • Pomona II: 44.9%

KNOW MORE

The load factor is the relation between the energy effectively generated by a farm along a period of time and the maximum it would be possible to produce in ideal conditions, along the same period of time. It is about not only the quality of wind but also the good performance and availability of the technology in the farm thanks to the best practices of operation and maintenance. 

Latest news

Dialogues with community

We shared dialogue sessions with community members where we operate. Purpose? Let us know more each other and make links in favour of s...

Multimedia

More information

Useful data

Location

Ruta Provincial N°4, Km 8 – Pomona (Río Negro)

Non-technical summary

  Download