After the commissioning of the Ullum Solar Farm 3 years ago, new investments will be made in Sierras de Ullum and Tocota III for USD 11...
Ullum is the first solar farm of our company. Acquired by Genneia in April 2018, it comes out from 3 constructive projects born within the framework of programme RenovAr 1.5: Ullum I (25MW), Ullum II (25MW) and Ullum III (32MW).
Being in operation as from December 2018, its construction required 10 months and employed 550 people at rush time. 283,320 photovoltaic panels are placed un a surface of about 300 hectares.
With a certified saving of 106,000 t of C02 emissions per year, as from 2020 our Ullum Solar Farm is authorized by the organization Verified Carbon Standard to issue Reduction Emissions Certificates.
Ullum Solar Farm has a load factor of almost 15 points over the world average, in all stages of the centre.
28.3% capacity factor
The load factor is the relation between the energy effectively generated by a farm along a period of time and the maximum it would be possible to produce in ideal conditions, along the same period of time. It is about not only the quality of wind but also the good performance and availability of the technology in the farm thanks to the best practices of operation and maintenance.
Multimedia
More information
Useful data
Location
Ruta Provincial N° 54, Km 9,5 - Ullum (San Juan)