With all the internal roads, assembly platforms and concrete foundations finished, begins the regressive account to complete the electrical work and installation of wind turbines
_____
Taking all necessary measures and meeting the provincial and national health protocols, works of stage II, III and IV of the North Wind Farm Chubut take impulse to approach its completion in the last quarter of the year. With civil works completed in early August, the next goals are to finish the electrical works and the manufacture and assembly of concrete towers.
In parallel, the assembly of wind turbines advances in the park. As for electrical work, work to complete the underground network of 33 kV Substation Transformadora and power line 132 (Kv), key engineering components that allow driving power generated by eros towards SADI (Argentine Interconnection System).
Meanwhile, in the industrial park of Puerto Madryn continues to manufacture and coupling of the remaining concrete towers to raise all the giants.
With all major components in the park, and several concrete towers finished, the assembly of eros continues apace, with the help of expert operators to control two main chains cranes (500 to 750 tons). RENEW awarded 2 parks Chubut III and IV North (developed in conjunction with Pan American Energy) are located very close to the city of Puerto Madryn, in the province of Chubut. His conclusion allowed to send 770,000 MWh per year of clean energy for Argentine homes.