With three giants already standing, 18 towers completed and almost 100% of civil works finished, a new project is coming to a successful close

_____

On April 12 the works of power were declared critical and priority by the national government and quickly, engineering and human capacity again turn as gears of a clock that works for wind projects Chubut North II, III and IV forward to good pace and achieve complete another project, this time on stage by challenging others under new schemes of work and rigorous protocols to contain the advance of the COVID-19.

Civil works are almost completed: these include all construction work that allow installation of wind turbines, such as internal roads and platforms for assembly and concrete foundations on which the giants will be installed.

In regard to components and materials for wind turbines, nacelles all games, hubs, drivetrains and shovels, transported in cargo ships from Germany, they are already on their respective platforms within the park.

In parallel, continues to manufacture concrete towers at the site in the Industrial Park of Puerto Madryn, with local labor. Electromechanical installation of some of the wind turbines task performed by experienced operators to control two main chains cranes (500 to 750 tons) was also initiated. So far, assembly 3 wind turbines and 18 towers were completed.

With equal pace advances the work at transformer station where the energy generated will be transported in the park to the Argentine Interconnection System. "This work involves the great challenge of coordinating many fronts, personnel and equipment amid a complicated and changing context. Despite the arrival of the cold, the spirit of the Genneia team work is very high, driven by the desire to complete another major project in unexpected conditions, "summarizes Federico Musante, manager of the project, this new demonstration of the commitment of the company with generating energía.